Multi-storey apartment complex planned for Limerick community


Large-scale housing development planned for Mungret
PLANNING permission is being sought for a major new housing development near Mungret, which could feature seven multi-storey apartment blocks.
Rockspring Developments is seeking planning permission from Limerick City and County Council to build 258 homes in the townland of Baunacloka.
According to the plans, a number of former commercial buildings at a site known locally as Fenton’s Yard - which was gutted by fire in 2022 - will be demolished.
In their place, would be 106 standard homes.


These will comprise one two-bed home, 98 three-bedroomed units and seven houses with four bedrooms.
A total of 152 apartments will be spread over seven blocks, ranging in height from four storeys to five storeys high.
If granted, the mix of apartments would see 37 one-bed units, 112 two-bed units and three three-bed units.
A creche will be provided, while the protected structure, Loughmore House, will be renovated, while neighbouring buildings will also be upgraded, and converted into a communal lounge for residents.
Access to the new estate will be from the existing road, the R526.
It’s not the first time Rockspring Developments has sought to build in the area.
In 2023, the company secured planning permission to construct 96 homes from Limerick City and County Council.
However, An Coimisiún Pleanála overturned this decision last year amid concerns that surface water drainage associated with the development would negatively impact the Lower River Shannon Special Area of Conservation.
In documents to council planners, agents for Rockspring said its rationale is to create “a high quality residential development, which enhances the environment and provides for a residential scheme appropriate to its context.”
Creche and apartment buildings at the site entrance would form a strong focal feature, added the agents.
Local councillor Daniel Butler has expressed concern at the plans, however.
“Locally, there is huge frustration about the immense traffic pressure an access point onto the R526 will create, alongside a glaring lack of wider community amenities in what is already a rapidly expanding area. Simply piling in hundreds of new houses and apartments without the necessary road infrastructure and public facilities is completely unsustainable. It feels as though we have learned nothing from the mistakes of the Celtic Tiger era, where we rushed to build houses while leaving growing communities behind without the essential services they need to thrive,” he said.
Planners are scheduled to make a decision on the project by the end of January next.