Water mains rehabilitation project continues to progress in Offaly area

The canal line to Pulloughplaceholder image
The canal line to Pullough

Uisce Eireann crews have now reached the halfway mark on the project in Pullough, with approximately 3km of the 6km scheme completed to date

Significant progress is being made on the water mains replacement project in Pullough, with works continuing to modernise the local water network and improve the resilience of the area's water infrastructure.

Uisce Eireann crews have now reached the halfway mark on the project, with approximately 3km of the 6km scheme completed to date. The installation of these new, modern water mains will strengthen the network, help reduce the risk of interruptions, and provide a more secure water supply for local homes and businesses.

The existing pipes were prone to bursts and leaks, leading to supply interruptions and the loss of treated drinking water, a valuable resource we all depend on.

Welcoming the progress made to date, Dave Murphy of Uisce Éireann said the project is continuing to deliver important improvements to the local water network. “Reaching the halfway mark is a significant milestone for this project and reflects the great progress our crews have made on the ground. With approximately 3km of new water mains installed so far, we are continuing to replace ageing infrastructure that has been prone to leaks and supply interruptions.

Every section of water main we replace helps to strengthen the network and improve the reliability of the water supply for local homes and businesses. Once complete, these upgrades will provide a more resilient water service for the Pullough community and help meet its needs for years to come."

The works, which commenced in August, are progressing as planned across two sections of the village. The first section extends from Pullough Community Shop & Café to the Turraun Nature Park car park. Work on the second section, between the Pull-Inn Pub and Cush Back Road, is due to commence shortly.

Works include installing new water service connections from the public water main on the road to customers’ property boundaries and linking them to customers’ water supply.

The project is being delivered by Shareridge on behalf of Uisce Éireann with completion expected by Spring 2027.

Customers can phone Uisce Éireann on 1800 278 278 if they have any questions about the project or visit the project page on the Uisce Éireann website for regular updates.

This project is one example of how Uisce Éireann works every day to reduce leaks. With more than 65,000 km of underground pipes nationally- enough to circle the earth one and a half times - fixing leaks can be complicated. Many are hidden, but we are making progress: National leakage is now at its lowest level ever, reduced from 49% in 2014 to 36% today.

To learn more about our National Leakage Reduction Programme visit: www.water.ie/projects-plans/national-projects/leakage-reduction-programme/