Further delay to Glen Rosa ferry is unacceptable, says Swinney


A further delay to a vastly late and over-budget ferry is “unacceptable”, the First Minister has said.
The Glen Rosa was due to be handed over by Government-owned yard Ferguson Marine in September of this year, but ferry operator CalMac – also publicly owned – could now be forced to wait until June 2026 to receive the ship.
Initially, both the Glen Rosa and its sister ship the Glen Sannox were due to cost £97 million and be in service between Arran and the mainland by 2018, but substantial delays caused by chaos at the yard have driven costs up to more than £400 million.
The Glen Sannox entered service earlier this year.
Speaking as he was challenged on the issue by the leaders of the Scottish Conservatives and Scottish Labour at First Minister’s Questions on Thursday, John Swinney said: “The time that it’s taken to build the Glen Rosa is unacceptable.


“This has obviously caused disruption to island communities and the Scottish Government is very focused on making sure, with the measures that the Deputy First Minister outlined yesterday, that early progress is made on the Glen Rosa and it can join the Glen Sannox in service at the earliest opportunity.”
Following news of the delay on Wednesday, Deputy First Minister Kate Forbes announced the establishment of a weekly review group to assess progress of the ship.
But Scottish Tory leader Russell Findlay pushed for accountability on the issue, describing the procurement of the vessels, led by Government-owned entity Caledonian Maritime Assets Limited (Cmal), as “corrupt” and highlighting Mr Swinney’s sign-off on the award during his time as finance secretary.
“He has never accepted blame, no-one in the SNP ever has or ever does,” Mr Findlay said.
“Not a single one of them has held their hands up to islanders or taxpayers.
“Half-a-billion pounds wasted, nearly a decade wasted, so who is responsible?”
Responding, the First Minister said he “unreservedly” accepts responsibility for “everything that happens in the name of my Government”, adding he and Transport Secretary Fiona Hyslop regularly engage with islanders about ferry services.


“Which is principally delivered through the fact that ferry travel to our island communities is significantly cheaper than the ferry services would have been had the Government not introduced road-equivalent tariff into our ferry services.
“So we’ve made ferry services more affordable for people in our island communities… we’re providing specific support to island communities that have been affected by disruption, and we’re investing in the new vessel fleet.
“That is this Government delivering on its commitments to support our island communities in Scotland.”
Labour leader Anas Sarwar also attacked the First Minister on the latest delays to the Glen Rosa – saying the bill for the two vessels will now cost more than £460 million.
“That’s nearly five times the original contract price,” Mr Sarwar told MSPs.
Rather than “steadying the ship”, he said Mr Swinney had been “unable to get a grip of this crisis” and accused the SNP of being “addicted to wasting people’s money”.


“Today I can reveal over £500 million has been spent fixing the ageing ferry fleet while over-budget vessels lay unfinished.”
Mr Swinney however stressed the investment the Scottish Government has made in the ferry fleet.
The First Minister told MSPs: “I am acutely conscious of the challenges on the island ferry network.
“But the network despite these issues performs very strongly for island communities and the Government’s investment will help to build that resilience in years to come.”
Addressing the delay, the yard’s new chief executive Graeme Thomson said: “We did not want to be in a position to push back the delivery of MV Glen Rosa.
“However, last year Ferguson Marine was forced to undertake necessary measures to mitigate against the risk of further delays to the completion of MV Glen Sannox.
“This included utilising key staff and sub-contractor resource from MV Glen Rosa and has had a knock-on impact on the shipyard’s ability to hit key build milestones on MV Glen Rosa, resulting in a delay to the timeline for delivery and an increase in costs.
“Our team are working extremely hard to deliver MV Glen Rosa and we are committed to completing the vessel as quickly and efficiently as possible.”
However, CalMac insisted the total spent on repairs was lower than Mr Sarwar had said, with the ferry operator saying the bill for this for 2015 to 2025 was £252,530,000.
A Calmac spokeswoman said: “This spend has been essential in order to maintain a reliable ferry service, as one third of our fleet of 35 vessels is operating beyond their life expectancy.
“We have had to invest more heavily in both planned and unplanned maintenance in recent years, and this investment grew to well over £43 million in 2023, compared with just £20 million in 2017.
“However, up to 12 new vessels are due to enter our fleet by 2029, including MV Isle of Islay this year, which will make a massive difference to our service, modernising a significant portion of our fleet and therefore reducing maintenance costs.”
A Scottish Government spokesperson said: “Just over £250 million has been spent on work to the Calmac fleet, which comprises more than 30 vessels, over the last 10 years.
“This does not just include repairs, but also work such as maintenance and upgrades.
“A third of the existing fleet is due to be replaced in the coming years.
“Total costs to deliver the Glen Sannox and Glen Rosa since public ownership are forecasted to be £418.25 million.
“This includes contingency costs of £12.5 million.”