Work will be undertaken to improve water supply in Tipperary's largest town

Upgrade to the treatment facilities at Monroe Water Treatment Plant

Work will be undertaken to improve water supply in Tipperary's largest town

The main construction works are planned to begin next month

Uisce Éireann says its concerted efforts to improve the water supply for customers in Clonmel is continuing, as works will soon commence to improve the security and resilience of the water supply across the town.

The water utility company says that the project, which represents a multi-million-euro investment in water infrastructure, will result in homes and businesses of Clonmel and surrounding areas being able to enjoy a safer, more secure water supply.

“In recent months, Uisce Éireann has carried out local remedial and improvement works to address the number of unplanned interruptions and water quality issues. This now marks the next stage in Uisce Éireann’s investment in Clonmel and will deliver a more robust, resilient water supply through upgraded treatment facilities, additional storage, and an upgraded network.

“The works will involve an upgrade to the treatment facilities at Monroe Water Treatment Plant (WTP); the installation of 15 kilometres of new water mains, as well as upgrades to the Rathronan Pump Station, which will connect the Monroe supply to the Clonmel North Reservoir and Poulavanogue network. It will address water quality risks for customers on the town’s Poulavanogue supply, allowing it to be taken off the EPA’s Remedial Action List”.

Uisce Éireann Water Regional Operations Manager, Jim Fitzgerald said: “This essential work is part of a significant investment by Uisce Éireann to improve the water infrastructure across Tipperary, prioritising investment where it is needed most.

“The upgrade of Monroe Treatment Plant and the construction of 15 kilometres of new water main will ensure a more robust, resilient water supply and significant enhancement to water security across the town. Towns like Clonmel have had to deal with periods of instability regarding their water supply.

“This project will significantly improve the security and resilience of the Clonmel supply and allow the community to thrive into the future.

“I thank the people of Clonmel for their ongoing support and patience throughout the delivery of this vital water infrastructure upgrade for the community,” he added.

The project will be carried out by Shareridge on behalf of Uisce Éireann.

Site investigation works will commence from August, with main construction works currently planned to commence in September. The works will take approximately 18 to 24 months to complete and will be carried out in phases to minimise disruption to the local community.

The works may require some short-term water interruptions, and Uisce Éireann says the project team will ensure that customers are given a minimum of 48 hours’ notice prior to any planned interruptions.

To continue reading this article,
please subscribe and support local journalism!


Subscribing will allow you access to all of our premium content and archived articles.

Subscribe

To continue reading this article for FREE,
please kindly register and/or log in.


Registration is absolutely 100% FREE and will help us personalise your experience on our sites. You can also sign up to our carefully curated newsletter(s) to keep up to date with your latest local news!

Register / Login

Buy the e-paper of the Donegal Democrat, Donegal People's Press, Donegal Post and Inish Times here for instant access to Donegal's premier news titles.

Keep up with the latest news from Donegal with our daily newsletter featuring the most important stories of the day delivered to your inbox every evening at 5pm.