Causeway Coast and Glens Council approves wind farm on Dungiven’s Benbradagh mountain

Despite concerns from the group Save Benbradagh and the receipt of over 1,400 objections, members approved plans for a four-turbine wind farm on Benbradagh Mountain.placeholder image
Despite concerns from the group Save Benbradagh and the receipt of over 1,400 objections, members approved plans for a four-turbine wind farm on Benbradagh Mountain.

Causeway Coast and Glens Council has given the green light to a new wind farm on a Dungiven mountain – despite almost 1,500 public objections.

Members of August’s Planning Committee approved an application for a wind farm, comprising up to four turbines with a 150-metre blade tip height, on Benbradagh mountain, on lands close to 175 Gelvin Road, in the townlands of Brishey and Curraghlane, and approximately 4.8 kilometres east of Dungiven.

Plans also include an electrical substation/control building, internal access tracks, spoil deposition areas, temporary construction compound, delivery route junction improvements and associated ancillary works.

A planning officer said Council recently received legal correspondence on behalf of the Save Benbradagh campaign group outlining issues regarding public rights of way, public access, and recreational pathways on the mountain, which they say must be “properly investigated before the application is determined”.

“It sets out details of a public right of way application, made to council on August 24 this year,” the officer added.

“It refers to public safety, access, tourism, and calls for matters to be properly identified and investigated and request that the application be adjourned, deferred or withdrawn from the [application] schedule.”

In response, the applicant said there was “no legal basis to seek injunctive relief”, adding that the right of way argument was “without foundation and wrong in law”.

“It states that the claimed right of way would not be obstructive, the rights of way referred to are speculative, tourism impacts are already considered in the environmental statement, and if the position of objectors was accepted this would delay the process by many years,” the officer clarified.

They added that Save Benbradagh’s correspondence “does not raise any new issues” with officers and that the farm, which lies within the Sperrin Area of Outstanding Natural Beauty (AONB), has been reduced from six to four turbines to “reduce the level of impact form viewpoint locations”.

They also noted that while Council has received 1,429 objections to the farm, with 526 in support, the farm will provide several environmental, economic, and social benefits, including “substantial” rates revenue, contributing towards the Climate Change Act target of 80% renewable energy by 2030, and the production of jobs.

On officers’ recommendation, members voted to approve the wind farm with 10 voting in favour and two abstentions.

Speaking afterwards, Sinn Féin Councillor Kathleen McGurk said: “Throughout this planning application process, my Sinn Féin colleagues have worked to ensure that the views of local residents were properly heard and represented. Benbradagh and the surrounding landscape are hugely important to the people who live here.

“That engagement helped secure a significant reduction in the scale of the original proposal, from six turbines to four, with the two most prominent turbines removed from the scheme. This is an important change which reduces the overall visual impact of the development and demonstrates the value of local people engaging with the planning process.

"Councillors on the Planning Committee are legally required to make decisions based on current planning policy. Planning officials recommended the application for approval, and there were no material planning grounds that would have allowed the application to be lawfully refused.

“Sinn Féin believes that increasing renewable generation will play an important role in improving energy affordability and security, to deliver lower and more stable energy costs by ending our reliance on imported fossil fuels, as well as delivering on our commitments to reduce emissions and creating new economic opportunities across the region.

"It is also our position that every planning application must be assessed on its own merits, in line with planning policy, and with real and meaningful consideration of community feedback.

"We will continue to support communities in engaging constructively with the planning system and ensure that future renewable energy development is delivered responsibly and sustainably."

Register
Follow us
© 2026 Formpress Publishing LTD. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice