Manorhamilton Chamber are providing regular updates on progress with the town's Public realm Works.
Here is the update for the week starting on Monday, April 24:
Area 1 - Old Church Street East
Ongoing paving to the footpath on Old Church Street East and Main Street in front of the Library which is scheduled to be completed early this week. All parking areas on the east side are paved with grouting to be completed along with footpaths this week. Partial footpath closures remain in place along sections of the works with directional signage in place directing users to cross safely to adjacent footpaths.
Area 2 - Market Square
Ongoing works at Market Square to continue, Footpath closure remains in place in front of the market yard, with directional signage in place directing users to cross safely to adjacent footpaths.
Area 3 - Old Church Street West
Paving of parking bay area to continue. Concrete works between existing footpath and new parking bays completed Friday 21st of April. Footpath closure will come into effect on this section early this week to facilitate drainage and ducting works. Users will be directed to use the footpath on the east side of Old Church Street.
If you have any queries in relation to the works, please speak with Gerry Hickey on site or email [email protected]