Work progresses at former Cemex site in Naas, Co Kildare


The €10m development is to include a warehouse, service station and electric vehicle charging facility
Work is progressing on a major new €10m development at the former Cemex site at Maudlins Roundabout, Naas, Co Kildare.
The development will include a warehouse, service station and electric vehicle charging facility.
At the centre of the development is a single-storey distribution centre with offices, extending to 9,383.85 square metres and reaching a maximum height of 19.5 metres. The facility will include 13 loading bays and associated service areas.
Construction is also underway on a new single-storey service station building with a gross floor area of 759.5 square metres. This will include a retail unit, three food offerings, a seating area, drive-thru hatch, toilets, back-of-house facilities and an external storage compound.
A separate drive-thru café building, measuring 256.7 square metres, is also being delivered as part of the scheme.
Also included in the development are a substation, external generator, service compound, water pump house and refuse compound.
Roof-mounted solar panels are being installed across buildings within the development.
Petrogas Group Ltd is carrying out the development, with construction having commenced in early February 2026 on the site.