Diversions in place as King's Island Flood Relief progresses in Limerick city

The King’s Island Flood Relief Scheme is well underway with construction works progressing across several sitesplaceholder image
The King’s Island Flood Relief Scheme is well underway with construction works progressing across several sites

The road closure at Sir Harry’s Mall will remain closed for an estimated 14 months to facilitate all phases of the project

A SERIES of significant road closures, some lasting over a year, have come into force around the King’s Island Flood Relief site, with local residents and commuters being advised to plan alternative routes.

Verdant Place is closed to all traffic for approximately five months, starting from August 11. Vehicles will be redirected along the route marked in blue and pedestrian access will follow the route marked in yellow.

The road closure at Sir Harry’s Mall will remain closed for an estimated 14 months to facilitate all phases of the project. During Phase 1a, vehicle traffic will follow a yellow diversion route, with access restricted to local residents only. Authorities are urging motorists to respect parking restrictions in the area, which is primarily residential.

A revised road layout is now in place at the Absolute Hotel, including new road markings and signage. Parking is prohibited on Long Lane opposite the hotel and double yellow lines are observed as this is a residential area.

Access must be maintained to all areas such as Abbey Lane and River Lane and there is strictly no parking allowed at entrances to these areas. Use alternative parking in Barringtons Car Park, Grove Island Car Park, Charlottes Quay Car Park.

Work is also due to commence in the coming weeks on Georges Quay, starting with the closure of the riverside footpath, followed by a full road closure. Dates have not yet been confirmed.

Ward & Burke Liaison Officer Elaine Cronin, is reminding everyone that Sir Harry’s Mall/St Frances Abbey area is a residential area. “Recently, there have been issues with vehicles parking illegally and blocking residents’ entrances.”

She continued: “Please be mindful and respectful when parking — please do not block driveways, gates, or access points, even for a short time. Your consideration will help maintain good relationships with the local community while works are ongoing.”

Ms Cronin also thanked locals for their continued support and patience during these essential works.

The King’s Island Flood Relief Scheme is designed to protect residents and properties from future flooding. Very significant flooding occurred in Spring 2014 when the existing defences failed locally, allowing flood waters onto the Island.